A running bill (also called an RA bill or IPC, interim payment certificate) is the periodic bill a contractor raises for work completed to date. Errors in it delay payment, so it is worth getting the steps right.
What goes into a running bill
- Measured quantities: work done this period, taken from the measurement book (MB) and signed off by the site engineer.
- BOQ rates: each item is billed at the contract rate in the Bill of Quantities.
- Cumulative vs previous: the bill shows the cumulative work to date, less what was billed in earlier bills.
- Deductions: retention money, advance recovery, and tax deductions as per your contract.
- VAT: applied as the contract and invoice rules require.
Step-by-step
- Record quantities in the measurement book as work is completed, with dates and site references.
- Get the quantities checked and countersigned by the supervising engineer.
- Price each item at its BOQ rate and compute the cumulative amount.
- Subtract the previous bill to get this period's amount.
- Apply retention and advance recovery, then taxes.
- Attach the supporting documents your client asks for, and submit.
Mistakes that delay payment
- Quantities that do not match the measurement book.
- Using a rate that is not in the contract BOQ.
- Forgetting to recover the advance or apply retention, then being asked to correct it.
- A bill that does not tie back to the previous certified bill.
Bill formats and required attachments vary by client and project, so confirm them in your contract.
Where NitiERP fits
NitiERP's construction software links BOQ items, measurement books, retention and advance recovery to running bill generation, with IRD CBMS billing for VAT invoices. See the construction ERP guide or book a free demo.